Tuesday, March 05, 2024

FUSION-SCI-FI-TEK

Contract for ITER vacuum vessel assembly

05 March 2024


The Sino-French TAC-1 consortium - led by China National Nuclear Corporation subsidiary China Nuclear Power Engineering and including Framatome - has been awarded a contract to assemble the vacuum chamber modules of the International Thermonuclear Experimental Reactor (ITER), under construction in Cadarache, southern France.

Representatives from the TAC-1 consortium companies (Image: CNNC)

ITER's plasma chamber, or vacuum vessel, houses the fusion reactions and acts as a first safety containment barrier. With an interior volume of 1400 cubic metres, it will be formed from nine wedge-shaped steel sectors that measure more than 14 metres in height and weigh 440 tonnes. The ITER vacuum vessel, once assembled, will have an outer diameter of 19.4 metres, a height of 11.4 metres, and weigh approximately 5200 tonnes. With the subsequent installation of in-vessel components such as the blanket and the divertor, the vacuum vessel will weigh 8500 tonnes.

The fabrication of the vacuum vessel sectors is shared between Europe (five sectors) and South Korea (four sectors). Vacuum vessel sector 6, at the centre of the assembly, and associated thermal shielding has already been manufactured and delivered by the Korean Domestic Agency. The first sector, 5, being supplied by Europe has now been manufactured in Italy and is undergoing factory acceptance tests prior to being shipped to the construction site.

Shen Yanfeng, deputy general manager of China National Nuclear Corporation, noted that the signing of the agreement means that the Chinese-French consortium has become the sole contractor for the installation of the Tokamak machine of the ITER project.

China formally agreed to join the ITER project in 2006. Since 2008, China has undertaken 18 procurement package tasks of research and manufacture, involving key components such as the magnet support system, magnet feeder system, power supply system, glow discharge cleaning system, gas injection system, and the 'first wall' of the reactor core, which is capable of withstanding extremely high temperatures.

In September 2019, the five-member Chinese-French consortium signed the TAC-1 installation contract with ITER, marking the beginning of China's in-depth participation in the tokamak. TAC-1 focuses on the assembly of the cryostat and cryostat thermal shield, the magnet feeders, the central solenoid, poloidal field and correction coil magnets, and cooling structures and instrumentation.

ITER is a major international project to build a tokamak fusion device in Cadarache, France, designed to prove the feasibility of fusion as a large-scale and carbon-free source of energy. The goal of ITER is to operate at 500 MW (for at least 400 seconds continuously) with 50 MW of plasma heating power input. It appears that an additional 300 MWe of electricity input may be required in operation. No electricity will be generated at ITER.

Thirty-five nations are collaborating to build ITER - the European Union is contributing almost half of the cost of its construction, while the other six members (China, India, Japan, South Korea, Russia and the USA) are contributing equally to the rest. Construction began in 2010 and the original 2018 first plasma target date was put back to 2025 by the ITER council in 2016. In June last year, the ITER Organisation was expected to reveal a revised timeline for the project but instead put back by a year an announcement on an updated timeline.

The revamped project plan for ITER - with modifications to its configuration, phased installation and new research schedule - is being finalised ahead of being submitted to the ITER Council in June.

Researched and written by World Nuclear News


MIT’s Superconducting Magnets Mark Major Fusion Milestone

  • MIT researchers achieve a world-record magnetic field strength using high-temperature superconducting magnets, demonstrating their potential for compact fusion power plants.

  • The comprehensive study, detailed in six peer-reviewed papers, validates the magnet's design and performance, offering a solid foundation for future fusion devices.

  • By leveraging new materials and innovative design approaches, MIT and its partners pave the way for practical fusion energy, promising a cleaner, limitless energy source for the future.


An MIT comprehensive study of high-temperature superconducting magnets confirms they meet requirements for an economic, compact fusion power plant.

A detailed report by researchers at PSFC and MIT spinout company Commonwealth Fusion Systems (CFS), published in a collection of six peer-reviewed papers in a special edition of the March issue of IEEE Transactions on Applied Superconductivity. Together, the papers describe the design and fabrication of the magnet and the diagnostic equipment needed to evaluate its performance, as well as the lessons learned from the process. Overall, the team found, the predictions and computer modeling were spot-on, verifying that the magnet’s unique design elements could serve as the foundation for a fusion power plant. Back during the predawn hours of Sept. 5, 2021, engineers achieved a major milestone in the labs of MIT’s Plasma Science and Fusion Center (PSFC), when a new type of magnet, made from high-temperature superconducting material, achieved a world-record magnetic field strength of 20 tesla for a large-scale magnet. That’s the intensity needed to build a fusion power plant that is expected to produce a net output of power and potentially usher in an era of virtually limitless power production.

The test was immediately declared a success, having met all the criteria established for the design of the new fusion device, dubbed SPARC, for which the magnets are the key enabling technology. Champagne corks popped as the weary team of experimenters, who had labored long and hard to make the achievement possible, celebrated their accomplishment.

But that was far from the end of the process. Over the ensuing months, the team tore apart and inspected the components of the magnet, pored over and analyzed the data from hundreds of instruments that recorded details of the tests, and performed two additional test runs on the same magnet, ultimately pushing it to its breaking point in order to learn the details of any possible failure modes.

Enabling practical fusion power

The successful test of the magnet, said Hitachi America Professor of Engineering Dennis Whyte, who recently stepped down as director of the PSFC, was “the most important thing, in my opinion, in the last 30 years of fusion research.”

Before the Sept. 2021 demonstration, the best-available superconducting magnets were powerful enough to potentially achieve fusion energy – but only at sizes and costs that could never be practical or economically viable. Then, when the tests showed the practicality of such a strong magnet at a greatly reduced size, “overnight, it basically changed the cost per watt of a fusion reactor by a factor of almost 40 in one day,” Whyte said.

“Now fusion has a chance,” Whyte added. Tokamaks, the most widely used design for experimental fusion devices, “have a chance, in my opinion, of being economical because you’ve got a quantum change in your ability, with the known confinement physics rules, about being able to greatly reduce the size and the cost of objects that would make fusion possible.”

The comprehensive data and analysis from the PSFC’s magnet test, as detailed in the six new papers, has demonstrated that plans for a new generation of fusion devices – the one designed by MIT and CFS, as well as similar designs by other commercial fusion companies – are built on a solid foundation in science.

The superconducting breakthrough

Fusion, the process of combining light atoms to form heavier ones, powers the sun and stars, but harnessing that process on Earth has proved to be a daunting challenge, with decades of hard work and many billions of dollars spent on experimental devices. The long-sought, but never yet achieved, goal is to build a fusion power plant that produces more energy than it consumes. Such a power plant could produce electricity without emitting greenhouse gases during operation, and generating very little radioactive waste. Fusion’s fuel, a form of hydrogen that can be derived from seawater, is virtually limitless.

Related: 2 Ways to Play Europe’s $800 Billion Energy Crisis

But to make it work requires compressing the fuel at extraordinarily high temperatures and pressures, and since no known material could withstand such temperatures, the fuel must be held in place by extremely powerful magnetic fields. Producing such strong fields requires superconducting magnets, but all previous fusion magnets have been made with a superconducting material that requires frigid temperatures of about 4º above absolute zero (4 kelvins, or -270º Celsius).

In the last few years, a newer material nicknamed REBCO, for rare-earth barium copper oxide, was added to fusion magnets, and allows them to operate at 20 kelvins, a temperature that despite being only 16 kelvins warmer, brings significant advantages in terms of material properties and practical engineering.

Taking advantage of this new higher-temperature superconducting material was not just a matter of substituting it in existing magnet designs. Instead, “it was a rework from the ground up of almost all the principles that you use to build superconducting magnets,” Whyte said. The new REBCO material is “extraordinarily different than the previous generation of superconductors. You’re not just going to adapt and replace, you’re actually going to innovate from the ground up.” The new papers in Transactions on Applied Superconductivity describe the details of that redesign process, now that patent protection is in place.

A key innovation: no insulation

One of the dramatic innovations, which had many others in the field skeptical of its chances of success, was the elimination of insulation around the thin, flat ribbons of superconducting tape that formed the magnet. Like virtually all electrical wires, conventional superconducting magnets are fully protected by insulating material to prevent short-circuits between the wires. But in the new magnet, the tape was left completely bare; the engineers relied on REBCO’s much greater conductivity to keep the current flowing through the material.

Zach Hartwig, the Robert N. Noyce Career Development Professor in the Department of Nuclear Science and Engineering. Hartwig has a co-appointment at the PSFC and is the head of its engineering group, which led the magnet development project explained, “When we started this project, in let’s say 2018, the technology of using high-temperature superconductors to build large-scale high-field magnets was in its infancy. The state of the art was small benchtop experiments, not really representative of what it takes to build a full-size thing. Our magnet development project started at benchtop scale and ended up at full scale in a short amount of time,” he added, noting that the team built a 20,000-pound magnet that produced a steady, even magnetic field of just over 20 tesla – far beyond any such field ever produced at large scale.

“The standard way to build these magnets is you would wind the conductor and you have insulation between the windings, and you need insulation to deal with the high voltages that are generated during off-normal events such as a shutdown.” Eliminating the layers of insulation, he says, “has the advantage of being a low-voltage system. It greatly simplifies the fabrication processes and schedule.” It also leaves more room for other elements, such as more cooling or more structure for strength.

Related: Artificial Intelligence Could Trigger a Natural Gas Boom in Europe

The magnet assembly is a slightly smaller-scale version of the ones that will form the donut-shaped chamber of the SPARC fusion device now being built by CFS in Devens, Massachusetts. It consists of 16 plates, called pancakes, each bearing a spiral winding of the superconducting tape on one side and cooling channels for helium gas on the other.

But the no-insulation design was considered risky, and a lot was riding on the test program. “This was the first magnet at any sufficient scale that really probed what is involved in designing and building and testing a magnet with this so-called no-insulation no-twist technology,” Hartwig said. “It was very much a surprise to the community when we announced that it was a no-insulation coil.”

Pushing to the limit … and beyond

The initial test, described in previous papers, proved that the design and manufacturing process not only worked but was highly stable – something that some researchers had doubted. The next two test runs, also performed in late 2021, then pushed the device to the limit by deliberately creating unstable conditions, including a complete shutoff of incoming power that can lead to a catastrophic overheating. Known as quenching, this is considered a worst-case scenario for the operation of such magnets, with the potential to destroy the equipment.

Part of the mission of the test program, Hartwig said, was “to actually go off and intentionally quench a full-scale magnet, so that we can get the critical data at the right scale and the right conditions to advance the science, to validate the design codes, and then to take the magnet apart and see what went wrong, why did it go wrong, and how do we take the next iteration toward fixing that . . . it was a very successful test.”

That final test, which ended with the melting of one corner of one of the 16 pancakes, produced a wealth of new information, Hartwig noted. For one thing, they had been using several different computational models to design and predict the performance of various aspects of the magnet’s performance, and for the most part, the models agreed in their overall predictions and were well-validated by the series of tests and real-world measurements. But in predicting the effect of the quench, the model predictions diverged, so it was necessary to get the experimental data to evaluate the models’ validity.

“The highest-fidelity models that we had predicted almost exactly how the magnet would warm up, to what degree it would warm up as it started to quench, and where would the resulting damage to the magnet would be,” he noted. As described in detail in one of the new reports, “That test actually told us exactly the physics that was going on, and it told us which models were useful going forward and which to leave by the wayside because they’re not right.”

Whyte commented, “Basically we did the worst thing possible to a coil, on purpose, after we had tested all other aspects of the coil performance. And we found that most of the coil survived with no damage,” while one isolated area sustained some melting. “It’s like a few percent of the volume of the coil that got damaged.” And that led to revisions in the design that are expected to prevent such damage in the actual fusion device magnets, even under the most extreme conditions.

Hartwig emphasizes that a major reason the team was able to accomplish such a radical new record-setting magnet design, and get it right the very first time and on a breakneck schedule, was thanks to the deep level of knowledge, expertise, and equipment accumulated over decades of operation of the Alcator C-Mod tokamak, the Francis Bitter Magnet Laboratory, and other work carried out at PSFC. “This goes to the heart of the institutional capabilities of a place like this,” he said. “We had the capability, the infrastructure, and the space and the people to do these things under one roof.”

The collaboration with CFS was also key, he said, with MIT and CFS combining the most powerful aspects of an academic institution and private company to do things together that neither could have done on their own. “For example, one of the major contributions from CFS was leveraging the power of a private company to establish and scale up a supply chain at an unprecedented level and timeline for the most critical material in the project: 300 kilometers (186 miles) of high-temperature superconductor, which was procured with rigorous quality control in under a year, and integrated on schedule into the magnet.”

The integration of the two teams, those from MIT and those from CFS, also was crucial to the success, he said. “We thought of ourselves as one team, and that made it possible to do what we did.”

**

It sounds like the past 2 ½ years have proven the immense value of the rare-earth barium copper oxide development. Even more impressive is that the team and its funders tried the no insulation technique and succeeded.

They have just put much better confinement power into the fusion effort.

And it won’t be just the tokomak devices getting the upgrade. Many of us still have a lot of confidence in the potential of the Robert Bussard based device and others.

Then there is the likelihood that superconducting magnet development will make more strides to higher temperatures.

Meanwhile Eric Lerner is working the plasma confinement idea and is improving steadily.

There just might be power plant choices sooner that the cynics could imagine.

By Brian Westenhaus via New Energy and Fuel


Tests show high-temperature superconducting magnets are ready for fusion


Detailed study of magnets built by MIT and Commonwealth Fusion Systems confirms they meet requirements for an economic, compact fusion power plant.


NEWS RELEASE 

MASSACHUSETTS INSTITUTE OF TECHNOLOGY

Fusion Magnets 

IMAGE: 

IN MIT’S PLASMA SCIENCE AND FUSION CENTER, THE NEW MAGNETS ACHIEVED A WORLD-RECORD MAGNETIC FIELD STRENGTH OF 20 TESLA FOR A LARGE-SCALE MAGNET.

view more 

CREDIT: IMAGE: GRETCHEN ERTL




In the predawn hours of Sept. 5, 2021, engineers achieved a major milestone in the labs of MIT’s Plasma Science and Fusion Center (PSFC), when a new type of magnet, made from high-temperature superconducting material, achieved a world-record magnetic field strength of 20 tesla for a large-scale magnet. That’s the intensity needed to build a fusion power plant that is expected to produce a net output of power and potentially usher in an era of virtually limitless power production.

The test was immediately declared a success, having met all the criteria established for the design of the new fusion device, dubbed SPARC, for which the magnets are the key enabling technology. Champagne corks popped as the weary team of experimenters, who had labored long and hard to make the achievement possible, celebrated their accomplishment.

But that was far from the end of the process. Over the ensuing months, the team tore apart and inspected the components of the magnet, pored over and analyzed the data from hundreds of instruments that recorded details of the tests, and performed two additional test runs on the same magnet, ultimately pushing it to its breaking point in order to learn the details of any possible failure modes.

All of this work has now culminated in a detailed report by researchers at PSFC and MIT spinout company Commonwealth Fusion Systems (CFS), published in a collection of six peer-reviewed papers in a special edition of the March issue of IEEE Transactions on Applied Superconductivity. Together, the papers describe the design and fabrication of the magnet and the diagnostic equipment needed to evaluate its performance, as well as the lessons learned from the process. Overall, the team found, the predictions and computer modeling were spot-on, verifying that the magnet’s unique design elements could serve as the foundation for a fusion power plant.

Enabling practical fusion power

The successful test of the magnet, says Hitachi America Professor of Engineering Dennis Whyte, who recently stepped down as director of the PSFC, was “the most important thing, in my opinion, in the last 30 years of fusion research.”

Before the Sept. 5 demonstration, the best-available superconducting magnets were powerful enough to potentially achieve fusion energy — but only at sizes and costs that could never be practical or economically viable. Then, when the tests showed the practicality of such a strong magnet at a greatly reduced size, “overnight, it basically changed the cost per watt of a fusion reactor by a factor of almost 40 in one day,” Whyte says.

“Now fusion has a chance,” Whyte adds. Tokamaks, the most widely used design for experimental fusion devices, “have a chance, in my opinion, of being economical because you’ve got a quantum change in your ability, with the known confinement physics rules, about being able to greatly reduce the size and the cost of objects that would make fusion possible.” 

The comprehensive data and analysis from the PSFC’s magnet test, as detailed in the six new papers, has demonstrated that plans for a new generation of fusion devices — the one designed by MIT and CFS, as well as similar designs by other commercial fusion companies — are built on a solid foundation in science.

The superconducting breakthrough

Fusion, the process of combining light atoms to form heavier ones, powers the sun and stars, but harnessing that process on Earth has proved to be a daunting challenge, with decades of hard work and many billions of dollars spent on experimental devices. The long-sought, but never yet achieved, goal is to build a fusion power plant that produces more energy than it consumes. Such a power plant could produce electricity without emitting greenhouse gases during operation, and generating very little radioactive waste. Fusion’s fuel, a form of hydrogen that can be derived from seawater, is virtually limitless.

But to make it work requires compressing the fuel at extraordinarily high temperatures and pressures, and since no known material could withstand such temperatures, the fuel must be held in place by extremely powerful magnetic fields. Producing such strong fields requires superconducting magnets, but all previous fusion magnets have been made with a superconducting material that requires frigid temperatures of about 4 degrees above absolute zero (4 kelvins, or -270 degrees Celsius). In the last few years, a newer material nicknamed REBCO, for rare-earth barium copper oxide, was added to fusion magnets, and allows them to operate at 20 kelvins, a temperature that despite being only 16 kelvins warmer, brings significant advantages in terms of material properties and practical engineering.

Taking advantage of this new higher-temperature superconducting material was not just a matter of substituting it in existing magnet designs. Instead, “it was a rework from the ground up of almost all the principles that you use to build superconducting magnets,” Whyte says. The new REBCO material is “extraordinarily different than the previous generation of superconductors. You’re not just going to adapt and replace, you’re actually going to innovate from the ground up.” The new papers in Transactions on Applied Superconductivity describe the details of that redesign process, now that patent protection is in place.

A key innovation: no insulation

One of the dramatic innovations, which had many others in the field skeptical of its chances of success, was the elimination of insulation around the thin, flat ribbons of superconducting tape that formed the magnet. Like virtually all electrical wires, conventional superconducting magnets are fully protected by insulating material to prevent short-circuits between the wires. But in the new magnet, the tape was left completely bare; the engineers relied on REBCO’s much greater conductivity to keep the current flowing through the material.

“When we started this project, in let’s say 2018, the technology of using high-temperature superconductors to build large-scale high-field magnets was in its infancy,” says Zach Hartwig, the Robert N. Noyce Career Development Professor in the Department of Nuclear Science and Engineering. Hartwig has a co-appointment at the PSFC and is the head of its engineering group, which led the magnet development project. “The state of the art was small benchtop experiments, not really representative of what it takes to build a full-size thing. Our magnet development project started at benchtop scale and ended up at full scale in a short amount of time,” he adds, noting that the team built a 20,000-pound magnet that produced a steady, even magnetic field of just over 20 tesla — far beyond any such field ever produced at large scale.

“The standard way to build these magnets is you would wind the conductor and you have insulation between the windings, and you need insulation to deal with the high voltages that are generated during off-normal events such as a shutdown.” Eliminating the layers of insulation, he says, “has the advantage of being a low-voltage system. It greatly simplifies the fabrication processes and schedule.” It also leaves more room for other elements, such as more cooling or more structure for strength. 

The magnet assembly is a slightly smaller-scale version of the ones that will form the donut-shaped chamber of the SPARC fusion device now being built by CFS in Devens, Massachusetts. It consists of 16 plates, called pancakes, each bearing a spiral winding of the superconducting tape on one side and cooling channels for helium gas on the other.

But the no-insulation design was considered risky, and a lot was riding on the test program. “This was the first magnet at any sufficient scale that really probed what is involved in designing and building and testing a magnet with this so-called no-insulation no-twist technology,” Hartwig says. “It was very much a surprise to the community when we announced that it was a no-insulation coil.”

Pushing to the limit … and beyond

The initial test, described in previous papers, proved that the design and manufacturing process not only worked but was highly stable — something that some researchers had doubted. The next two test runs, also performed in late 2021, then pushed the device to the limit by deliberately creating unstable conditions, including a complete shutoff of incoming power that can lead to a catastrophic overheating. Known as quenching, this is considered a worst-case scenario for the operation of such magnets, with the potential to destroy the equipment. 

Part of the mission of the test program, Hartwig says, was “to actually go off and intentionally quench a full-scale magnet, so that we can get the critical data at the right scale and the right conditions to advance the science, to validate the design codes, and then to take the magnet apart and see what went wrong, why did it go wrong, and how do we take the next iteration toward fixing that. … It was a very successful test.”

That final test, which ended with the melting of one corner of one of the 16 pancakes, produced a wealth of new information, Hartwig says. For one thing, they had been using several different computational models to design and predict the performance of various aspects of the magnet’s performance, and for the most part, the models agreed in their overall predictions and were well-validated by the series of tests and real-world measurements. But in predicting the effect of the quench, the model predictions diverged, so it was necessary to get the experimental data to evaluate the models’ validity.

“The highest-fidelity models that we had predicted almost exactly how the magnet would warm up, to what degree it would warm up as it started to quench, and where would the resulting damage to the magnet would be,” he says. As described in detail in one of the new reports, “That test actually told us exactly the physics that was going on, and it told us which models were useful going forward and which to leave by the wayside because they’re not right.”

Whyte says, “Basically we did the worst thing possible to a coil, on purpose, after we had tested all other aspects of the coil performance. And we found that most of the coil survived with no damage,” while one isolated area sustained some melting. “It’s like a few percent of the volume of the coil that got damaged.” And that led to revisions in the design that are expected to prevent such damage in the actual fusion device magnets, even under the most extreme conditions.

Hartwig emphasizes that a major reason the team was able to accomplish such a radical new record-setting magnet design, and get it right the very first time and on a breakneck schedule, was thanks to the deep level of knowledge, expertise, and equipment accumulated over decades of operation of the Alcator C-Mod tokamak, the Francis Bitter Magnet Laboratory, and other work carried out at PSFC. “This goes to the heart of the institutional capabilities of a place like this,” he says. “We had the capability, the infrastructure, and the space and the people to do these things under one roof.”

The collaboration with CFS was also key, he says, with MIT and CFS combining the most powerful aspects of an academic institution and private company to do things together that neither could have done on their own. “For example, one of the major contributions from CFS was leveraging the power of a private company to establish and scale up a supply chain at an unprecedented level and timeline for the most critical material in the project: 300 kilometers (186 miles) of high-temperature superconductor, which was procured with rigorous quality control in under a year, and integrated on schedule into the magnet.” 

The integration of the two teams, those from MIT and those from CFS, also was crucial to the success, he says. “We thought of ourselves as one team, and that made it possible to do what we did.”

Written by David L. Chandler, MIT News Office

Papers: Special issue on the SPARC Toroidal Field Model Coil Program

https://ieeexplore.ieee.org/xpl/tocresult.jsp?isnumber=10348035&punumber=77

 


 

Nonproliferation, national security, nuclear energy, infrastructure resilience and climate teams from Argonne earn Secretary of Energy Honor Awards


Six groups of Argonne researchers net top awards for climate science, nuclear technologies, infrastructure resilience and national security efforts


Grant and Award Announcement

DOE/ARGONNE NATIONAL LABORATORY

Argonne-1600x900 

IMAGE: 

ARGONNE NATIONAL LABORATORY.

view more 

CREDIT: (IMAGE BY ARGONNE NATIONAL LABORATORY.)




Extraordinary work by Argonne teams garners awards that celebrate a combination of specialized capabilities, collaboration and common purpose.

Researchers from the U.S. Department of Energy’s (DOE) Argonne National Laboratory are part of six groups that received 2023 Secretary of Energy Honor Awards. The awards are considered among the highest forms of recognition that can be bestowed by DOE.

Secretary Jennifer Granholm recognized the broad-sweeping impact of award-winning teams with unique specialties but common and ​“amazing purposes” in a ceremony on Feb. 20. Deputy Secretary David Turk and undersecretaries from across the federal agency acknowledged individuals and provided project specifics.

Five of the groups that received team Achievement Awards featured members of Argonne’s Nuclear Technologies and National Security (NTNS) directorate. A sixth multilaboratory group that received an Achievement Award for Leadership in Climate Action included Rao Kotamarthi, a senior scientist in Argonne’s Environmental Science division (EVS) in the Computing, Environment and Life Sciences directorate. Kotamarthi’s work included funding from AT&T and DOE’s Biological and Environmental Research program, as well as several other government and industry sponsors.

“We treasure the teamwork that turns individual expertise into global impact.” — John G. Stevens, Argonne National Laboratory

Jiali Wang, another EVS scientist, and Bonnie Basiorka, from Argonne’s Financial Management and Procurement Services (FMPS) directorate, were recognized for their contributions to NTNS-led projects.

“Congratulations to our colleagues on earning the highest recognition from the Secretary of Energy,” said Argonne Director Paul Kearns. ​“These honors exemplify some of the pivotal discoveries and global impact that our world-class community of talent achieves here at Argonne. Their accomplishments also underscore the success of the NTNS directorate since its establishment only two years ago and the strength of our EVS and FMPS teams.”

NTNS’s five remarkable Honors Awards

The first award announcements for Argonne’s NTNS directorate came to two groups dedicated to nuclear nonproliferation research and development. The two projects were funded by National Nuclear Security Administration’s Office of Defense Nuclear Nonproliferation in what is now the Office of Reactor Conversion and Uranium Supply.

The first team featured 13 people who worked to make nuclear fuels and processes safer in Germany. The Achievement Award granted to the German FRM-II Low-Enriched Uranium Conversion Team recognized Aurelian Bergeron, Cezary Bojanowski, Thad A. Heltemes, Jeremy Richard Licht, Basar Ozar, Francesc Puig, Jordi Roglans-Ribas, Marta Anna Sitek and John G. Stevens from NTNS’s Nuclear Science and Engineering division and Gerard L. Hofman, Yeon Soo Kim, Abdellatif M. Yacout and Bei Ye from NTNS’s Chemical and Fuel Cycle Technologies division.

The second team featured 14 people working on a project involving molybdenum-99, a valued isotope used in medical procedures whose purification process needed to be re-examined during conversion efforts. The Achievement Award granted to the International Molybdenum-99 Conversion Team included Bonnie Basiorka from Argonne’s FMPS directorate; M. Alex Brown, William L. Ebert, Artem Gelis, now at University of Nevada, Las Vegas, James L. Jerden, Peter Tkac, George Vandegrift and Amanda J. Youker from NTNS’s Chemical and Fuel Cycle Technologies division; and Karen R. Grudzinski, Thad A. Heltemes, John W. Holland, Jordi Roglans-Ribas, John G. Stevens and Caryn Warsaw from NTNS’s Nuclear Science and Engineering division.

“We treasure the teamwork that turns individual expertise into global impact,” said John G. Stevens, an NTNS program manager in reactor material management who was recognized for his work on both teams. ​“These are remarkable individuals and deeply impactful teams who finish daunting tasks with creativity and persistence.”

One group was recognized with an Achievement Award for impact in national security. The DOE Ukraine Response Team included five Argonne honorees from NTNS’s Nuclear Science and Engineering division and Strategic Security Sciences division. They conducted nuclear safety and security assessments and supported large-scale shipments that helped secure nuclear energy infrastructure to mitigate risk in Ukraine. This work was done for NNSA. NTNS’s Thomas Fanning, senior advisor to the assistant secretary for nuclear energy, received an Achievement Award for his part in the DecaBDE Response Team, which addressed impacts on the nuclear industry of an Environmental Protection Agency ruling prohibiting distribution in commerce of a specific flame retardant used in wire and cable insulation. The project was done for DOE’s Office of Nuclear Energy.

A fifth Achievement Award celebrating NTNS efforts recognized work by the Puerto Rico Grid Recovery & Modernization Team. Three scientists from NTNS’s Decision and Infrastructure Sciences division — Susan Jones, Lawrence Paul Lewis and John Murphy — were honored with Jiali Wang from the EVS division. The team’s creativity, steadfastness and collaboration will ensure that the pathways toward a 100% renewable energy transition for Puerto Rico promote energy justice, bolster infrastructure resilience and are adapted to future climate risks. This work was funded through an interagency reimbursable work agreement between DOE, DOE’s Grid Deployment Office and the Federal Emergency Management Agency.

Argonne National Laboratory seeks solutions to pressing national problems in science and technology. The nation’s first national laboratory, Argonne conducts leading-edge basic and applied scientific research in virtually every scientific discipline. Argonne researchers work closely with researchers from hundreds of companies, universities, and federal, state and municipal agencies to help them solve their specific problems, advance America’s scientific leadership and prepare the nation for a better future. With employees from more than 60 nations, Argonne is managed by UChicago Argonne, LLC for the U.S. Department of Energy’s Office of Science.

The U.S. Department of Energy’s Office of Science is the single largest supporter of basic research in the physical sciences in the United States and is working to address some of the most pressing challenges of our time. For more information, visit https://​ener​gy​.gov/​s​c​ience.