Saturday, September 21, 2024

 

GERMANY


Environmental challenge to Konrad repository dismissed



Thursday, 19 September 2024

The Lower Saxony Ministry of the Environment has rejected an application from environmental groups NABU and BUND to revoke or withdraw the planning approval decision for the Konrad repository for low and intermediate-level radioactive waste.

Environmental challenge to Konrad repository dismissed
The former Konrad mine (Image: BGE)

The former Konrad iron ore mine - in Salzgitter, Lower Saxony - closed for economic reasons in 1976 and investigations began the same year to determine whether the mine was suitable for use as a repository for low and intermediate-level radioactive waste (LLW/ILW).

In 2002, the Lower Saxony Ministry for the Environment issued a planning approval decision for the Konrad repository. Following multiple legal proceedings, this approval was confirmed by the Federal Administrative Court in 2007. A construction licence was issued in January 2008.

However, in May 2021, NABU and BUND submitted an application to withdraw or revoke the existing planning approval decision for the Konrad repository and to stop construction.

The Lower Saxony Ministry of the Environment has now dismissed the application "after intensive legal and substantive review".

Federal radioactive waste company, Bundesgesellschaft für Endlagerung (BGE) - which assumed responsibility as the operator of the Konrad repository from the Federal Office for Radiation Protection in April 2017 - welcomed the decision.

"This finding once again confirms that the planning approval decision for the Konrad repository is legal," it said. "BGE will continue to push ahead with the construction of the Konrad repository so that the majority of low and medium-level radioactive waste from Germany can be safely disposed of."

Thomas Lautsch, technical director of BGE, added: "With the planning approval decision for the Konrad repository, we have a robust basis for the construction, operation and decommissioning of the Konrad repository. The construction will take place on this basis and will also be implemented in accordance with the current technical regulations."

The Konrad mine is being converted for use as a repository under the supervision of BGE. The two mine shafts are being renovated and equipped with the necessary infrastructure underground. Among other things, this infrastructure includes transport galleries and the emplacement areas at a depth of around 850 metres. Above ground, construction work is under way on new buildings, including the reloading hall.

The final disposal of up to 303,000 cubic metres of LLW/ILW at Konrad is set to begin in the early 2030s. This waste represents 95% of the country's waste volume, with 1% of the radioactivity. At present, this waste is stored above-ground in interim storage facilities at more than 30 locations in Germany. Once within the Konrad repository, the containers will be immobilised with suitable concrete and securely sealed off during emplacement operations. Once operations are complete, all cavities of the mine will be backfilled and sealed in a manner that ensures long-term safety.

No comments: