Friday, April 14, 2023

Righting toppled US ship in drydock will be 'very complicated', warns marine expert

Investigationsm are ongoing into why the vessel owned by the US Navy toppled over in the dry dock (Picture: PA).

Workers face a "very complicated" task of righting a vessel which toppled over while in drydock, a marine expert said as investigations into the incident continue.

Two huge cranes have been placed next to the US Navy vessel the Petrel, which tipped to a 45-degree angle last month, leaving 35 people injured.

The incident sparked a huge emergency service operation at the drydock in Leith, Edinburgh, which is operated by Dales Marine Services.

Iraklis Lazakis, of the University of Strathclyde, said the two cranes are at the vessel’s port side but “no other specific action can be speculated on about righting the vessel”, which he said would be a “very complicated procedure”.

Police remain at the scene, and on Thursday a police car could be seen as workers operated the cranes and moved around the stricken 3,371-tonne vessel.

Both the Health and Safety Executive (HSE) and Police Scotland said investigations into the incident, which happened on March 22, are continuing.

A view of the ship Petrel at Imperial Dock in Leith, Edinburgh, which became dislodged from its holding on Wednesday March 22 (Picture: PA).

An HSE spokesman said: "Specialist inspectors from HSE are assessing the technical aspects of the structural collapse and continue to work with Police Scotland on the investigation into this incident."

Dr Lazakis, of the Department of Naval Architecture, Ocean and Marine Engineering, said for the ship to be put upright a number of aspects need to be considered, including "the potential damage on the outer hull of the vessel on the starboard side, any internal structural damages or otherwise, any transfer of loads internally, and any movements of the keel blocks due to the shifting of the ship".

He added: "One would also need to consider the lifting capacity/radius and angle of lift of the cranes in relation to the ship's lightweight – or lightship – as well as any additional weights or loads within the ship.

'A very complicated procedure'

Dr Lazakis added: "Another way to bring the ship up would be by initially assessing its structural condition externally and internally and shifting of loads etc, as well as performing any repairs needed on the outer hull, repositioning the keel blocks in the drydock if needed as per the ship’s docking plan, then starting to flood the drydock very slowly and tilting the vessel upright gradually.

"Overall, this is a very complicated procedure, also considering that, as I understand it, the drydock is used by another vessel I believe.

"I cannot speculate on how long this would take as there are so many unknowns at the moment."

The Petrel

The 76m-long Petrel was once owned by the late Microsoft co-founder Paul Allen, who bought the ship to locate historically significant shipwrecks and discovered 30 sunken warships, including the Japanese Imperial Navy's IJN Musashi.

But in 2022 the Isle of Man-registered vessel was sold to the US Navy and is now operated by American-owned firm Oceaneering International.

The Petrel has been moored at Imperial Drydock in Leith since September 3, 2020, due to "operational challenges" from the pandemic.

Twenty-three people injured in the incident were taken to hospital and 12 were treated at the scene.

No comments: