Tuesday, November 17, 2026

 

Trial power supply begins at Bangladesh’s first nuclear plant

17.11.2026

Bangladesh has begun producing electricity from one of its two nuclear power plants, supplying 350 megawatts of electricity to the national grid on a trial basis for the first time.

The power supply from one of the two units of the Rooppur Power Plant began at 3:16 pm (0916 GMT), a press statement from the Bangladesh Atomic Energy Commission said on Tuesday.

The Russian-financed power plant was built in Ishwardi town in the Bangladeshi district of Pabna, more than 150 kilometres north-west of the capital Dhaka.

Electricity generated during the initial phase is scheduled to be supplied to the national grid for about 8 to 10 hours to monitor the performance and stability of the plant’s turbine, generator, and operating systems integrated with the national grid, according to the statement.

The plant will then be disconnected from the grid for necessary technical tests, and after a break of about 28 hours, it is scheduled to be reconnected for 4 to 6 hours to complete further tests, it added.

Connecting the plant to the national grid did not mean the start of commercial operation of the plant, said Zahedul Hasan, chief of Nuclear Power Plant Company Bangladesh Limited, an entity that will oversee the commercial operation of the plant.

“It was an important technical test to assess the compatibility of the plant’s electricity with the national grid and the grid’s capacity to receive the power,” he said.

The next phase of testing would proceed once the results of the trial connection are satisfactory, he added.

Commercial operation is likely to begin after a 10-month trial phase, as per the agreement with Russian contractors.

Bangladesh has built two nuclear power plants, each with a production capacity of 1,200 megawatts of electricity, with financial and technical support from Russia under a $12.65 billion Intergovernmental Credit Agreement signed in 2015.

The project is expected to play an important role in meeting Bangladesh’s growing electricity demand, ensuring energy security, and supporting sustainable power generation, the press release said.